Grocery / Specialty Food Retail

International Grocery with Butcher, Bakery and Hot Table

A two-location grocery operator took over a vacated anchor unit for their third store. Refrigeration, a butcher counter and a hot table turned a retail fit-out into a food-premises project.

Location
Cambridge, ON
Size
9,200 sq ft
Timeline
25 weeks, blueprint to open
Budget band
$1.4M–$1.75M

25 wks

Blueprint to open

186 ft

Refrigerated case run

3rd

Location for the operator

A two-location grocery operator wanted a third store and had found a vacated anchor unit in a Cambridge plaza. Big footprint, decent parking, rent that worked. Their previous two stores had been straight dry-and-packaged retail. This one was going to add a butcher counter, an in-house bakery and a hot table, and that is the point where a retail fit-out becomes a food premises with three separate operational risk profiles under one roof.

They had built the last store themselves with a general contractor and a refrigeration supplier working from different drawings. It took eleven months. They did not want to repeat that.

The challenge

Refrigeration drove everything. The case plan called for 186 linear feet of open multi-deck and reach-in cases plus four walk-ins — cooler, freezer, meat prep and a dedicated produce box. That is a parallel rack system on the roof, and the existing roof structure had been designed for a retail tenant with rooftop units for HVAC only. Placement of the rack, the condensers and the associated curbs needed a structural review before a single case was ordered, and two of the three logical locations were over the open-span portion of the deck.

Electrical was the second constraint. The unit was served at 347/600V with 400A. Total connected load with the rack, the case circuits, the bakery deck oven and rotary rack oven, the hot table and the general lighting came out well past that. The service went to 800A, and the utility’s disconnect location put the new metering on the opposite side of the building from the existing room.

Third, the departments each triggered their own requirements. A butcher counter needs a separate prep room with its own handwash, its own sanitizing sink, cleanable wall and ceiling finishes to the deck, and a floor sloped to drain. The bakery needs a Type 1 hood over the deck oven and a Type 2 over the proofers. The hot table needs a Type 1 canopy plus a hand sink within the required travel distance, and it changes the occupancy classification of that portion of the space. Region of Waterloo Public Health reviews all three as one submission but assesses them separately.

What NHFC did

Discover. We started with a load and layout study, not a floor plan. Case run, walk-in volumes, oven schedule and hot table capacity were locked before any architectural work, because those numbers determine the electrical service, the structural review and the roof plan — and all three of those have long lead times.

Lease terms were still open, so we used the study to negotiate the landlord’s contribution toward the service upgrade and roof reinforcement, on the argument that both are base-building improvements that outlive the tenancy.

Design. One coordinated set covering architectural, structural, mechanical, electrical and refrigeration. Norpex produced the case and equipment layout; we reconciled it against the drain plan, the rack piping runs and the electrical panel schedule before purchase orders went out. Structural reinforcement for the rack platform was designed and permitted at the same time as the interior work rather than as a later revision.

Build. Pasha Construction handled demolition of the old retail fixturing, the structural steel for the rooftop platform, and the extensive floor work — trench drains through the meat and bakery prep rooms, sloped pours, and the base slab repairs left behind by the previous tenant’s fixture anchors. Shop Flooring supplied a heavy-duty resinous system for the prep rooms and a sealed polished finish for the sales floor, which is the finish decision that keeps the $/sq ft on a grocery reasonable even when the equipment package is not.

Refrigeration piping, rack set and case placement ran on a dedicated critical path with its own weekly check-in, because in a grocery it is the schedule.

Deliver. Refrigeration was pulled down, temperature-logged for 72 hours and verified across every case and walk-in before a single pallet of product was loaded. It is the longest item on a grocery closeout list and the one that cannot be compressed. Health unit plan review was approved with the butcher room, bakery and hot table each signed off in the same submission. TSSA approved the gas connections to the bakery ovens and the hot table, and ESA cleared the 800A service and the case circuits without deficiencies.

The outcome

Twenty-five weeks from blueprint to open, against eleven months on their previous store. Cases were stocked over four days ahead of opening with the rack already stable at setpoint, which is the only way to load a grocery without throwing product away.

Cost landed at roughly $165 per square foot all-in, which reads low for a food premises until you account for grocery economics: the finishes are cheap and the refrigeration is not.

Scope at a glance

  • Refrigeration load and layout study ahead of architectural design
  • Lease negotiation support covering service upgrade and roof reinforcement cost sharing
  • Coordinated architectural, structural, mechanical, electrical and refrigeration drawings
  • 800A 347/600V service upgrade with relocated metering
  • Structural steel platform for parallel rack and remote condensers
  • 186 ft of refrigerated case line and four walk-in boxes
  • Butcher prep room: separate handwash, sanitizing sink, washable finishes to deck, trench drain
  • In-house bakery: Type 1 hood over deck oven, Type 2 over proofing
  • Hot table with Type 1 canopy and code-compliant hand sink placement
  • Resinous prep-room flooring and sealed polished sales floor
  • Building permit, ESA, TSSA, Region of Waterloo Public Health plan review and pre-opening inspection
  • 72-hour refrigeration temperature verification before product load

Free Consultation

Tell us what you want to build.

The first consultation is free. You get a project review, a realistic timeline and a preliminary cost breakdown — including an honest answer if the project does not work as scoped.

Mon – Fri, 9:00 a.m. – 5:00 p.m. · No obligation

Call usStart your project